YESCO Manufacturing and Corporate Office Building

The YESCO Manufacturing Facility and Corporate Office Building was constructed in only eight months (including a full season of harsh winter weather). Utilizing the tallest Tilt-Up panels ever constructed in Utah, the 66.5-foot tower provides additional signage on the freeway side of the building, which is essential for this sign company. The building is designed around the corporation’s commitment to lean process implementation for both the office and manufacturing components.

The Tilt-Up concrete provides the durability required in the manufacturing areas, while also allowing for large sections of glass in the offices for views and natural lighting. The concrete structure is ideal for minimizing unwanted noise pollution (from nearby freeway and airport traffic), and requires little if any maintenance. Energy saving strategies were also incorporated. This building is an example of creating dynamic spaces utilizing simple, cost-effective shapes and materials.

 
Main banner image for YESCO Manufacturing and Corporate Office Building

Project Location

Salt Lake City, UT 84104
United States

Project Images

TILT-UP TODAY MAGAZINE / PROJECTS IN THE NEWS

Project Team

General Contractor:
 
Concrete Contractor:
 
Architect:
 
Engineer:
 
Suppliers:
 
Photographer(s):

Project Specifics

Project Category:
Production/Manufacturing
Building Types:
Finishes:
Features:
Insulation:
Environmental:
Number of Floors:
0
Number of Panels:
73 panels
Total Floor Area:
104,000 sq ft (9,662 sq m)
Project Footprint:
90,000 sq ft (8,361 sq m)
Tallest Panel:
66 ft 6 in (20.27 m)
Widest Panel:
50 ft 7 in (15.42 m)
Largest Panel:
1,596 sq ft (148.3 sq m)
Tallest Cantilever:
20 ft 2 in (6.15 m)
Longest Spandrel:
49 ft 4 in (15.06 m)