Dixie Middle School

2015 TCA Tilt-Up Achievement Award - Educational Division

Article tools: Coming soon!

In order to obtain cost efficient buildings, the Washington County School District, for the past many years, has been constructing their educational facilities with concrete tilt-up. This economical option makes for faster construction.

This project was not only a challenge to design but also to build. Concrete tilt-up panels varied greatly in geometry. There were many spandrel and cantilevered panels to accommodate entryways, large openings, etc. Sandwich panels were used in some locations for exterior walls in areas that required a durable wall surface. Some of these areas were the gymnasium, wrestling room, cabinet shop, welding shop, etc. Due to the complexity of the panels, an elevation of every concrete tilt-up panel was done not only architecturally but also structurally. The project included tilt-up panels next to CMU and there was creativity in attaching the tilt-up panels with unseen connections.

The school district not only got a cost efficient high school campus, but due to the tilt-up panel construction, the building was able to be constructed in 20 months. Many school officials from other districts have expressed that they are amazed at how great the facility looks, especially when they realize how it was constructed and the associated cost. When the cost of construction was compared to other high schools under construction in Utah around the same time, the Washington County School District got "more building" for less money. Upon seeing the Dixie Middle School campus, it is assumed, based on how the school campus looks, that it must have cost much more to construct than it did.

Photos

Project Specifics

Project Wall Area
40,969 sq ft
(3,806 sq m)
Project Floor Area
164,896 sq ft
(15,319 sq m)
Tallest Panel
31 ft 4 in
(9.55 m)
Widest Panel
37 ft 11 in
(11.56 m)
Largest Panel
980 sq ft
(91.0 sq m)
Heaviest Panel
76,150 lbs
(34,541 kg)

Participating TCA Members

BHB Consulting Engineers PC
Project engineer
HK Composites, Inc.
Insulation systems
HD Supply Construction & Industrial White Cap
Tilt-up accessories

About the TCA

Founded in 1986, the Tilt-Up Concrete Association (TCA) strives to improve the quality and acceptance of site-cast Tilt-Up construction, a method in which concrete wall panels are cast on-site and tilted into place. Tilt-Up construction is one of the fastest growing industries in the United States, combining the advantages of reasonable cost with low maintenance, durability, speed of construction and minimal capital investment. At least 10,000 buildings, enclosing more than 650 million square feet, are constructed each year using this construction method.

Follow Us

We use LinkedIn, Twitter and YouTube to disseminate information about the Tilt-Up industry, gain new members and inform developers, owners and architects about the benefits of using Tilt-Up.

Popular Links

The following bookmarks jump to the most popular destinations on this site.