Where can I obtain information on necessary crane rigging, sling lengths, boom length and spreader bars?

The rigging configuration, spreader bar length and sling lengths are specified in the erection booklet prepared by the erection designer. The crane size and boom lengths are determined by the crane company.

At what phase of the job should I plan the erection sequenced?

Before the panels are cast, have the crane company representative assist in the layout to ensure that the panels can be lifted in the sequence cast.

What safety precautions are necessary before and during lifting?
  • Provide the crane company with a set of panel lifting details well before the day of lifting so that they can plan necessary rigging.
  • Double-check that the rigging configuration and that the spreader bars and slings are the correct length.
  • Watch for ditches, holes and overhead obstructions that might prevent the crane from moving.
  • Have a safety meeting at the beginning of the erection to ensure that everyone knows what is expected and how to operate safely.
  • Make certain everyone on the rigging crew knows how the lifting hardware is supposed to work.

 

 

 

Related Content

Here are a few other links that you might be interested in.

Tilt-Up Construction Basics

Benefits of Tilt Construction

Upcoming TCA Events

Member Resources

Access member resources for unique literature and other information.

Not a member?

Join Today!