Emulex Corporate Campus

Emulex Corporate Campus

2006 Tilt-Up Achievement Award Winner :: Office Division

Submitted by: Oltmans Construction Co.

Needing additional space quickly, the owner selected Tilt-Up for this facility because of its speed of construction and cost-effectiveness. The contractor employed widely regarded concrete installation techniques using laser-guided equipment to deliver a structurally solid building in earthquake prone southern California.

The unique infrastructure of the buildings included specialized cabling for the lab and the acoustic ceilings that needed to reduce noise and vibration from equipment. It was important to increase some base flooring and wall depth in order to help keep the disruptions from the computer equipment minimized.

Another challenge was deciding how everything was going to be cabled for both power and the networks. The result was a sophisticated cabling system that kept cables out of the way while making it easy for engineers to connect, disconnect and move equipment within the complex as needed.

The primary color palette of blue, caramel, gold and black was utilized in all aspects of the project. A dramatic glass curtain wall framed by the offset eastern façades of the other two buildings marks the main entry lobby. Floor-to-ceiling glass-enclosed walkways connect the buildings and 9-foot ceilings with floor-to-ceiling windows create a dramatic effect.

TCA Member Participants

Oltmans Construction Co. (Whittier, California)
Role: General Contractor, Tilt-Up Contractor
Dayton Superior Corporation (Miamisburg, Ohio)
Products: Lifting Hardware

The purpose of the TCA Awards Program is to recognize outstanding site cast Tilt-Up structures and advances in technology, products and methods used in the Tilt-Up industry. For more information on the program, submittal requirements and deadline dates, please refer to the awards submittal information page.

If you have further questions, please contact Jim Baty by email or by phone at (319) 895-6911.

Project Information

Emulex Corporate Campus
3450 E. Miraloma Avenue
Anaheim, CA 92806

Photographs

Click on any photo to enlarge it

Emulex Corporate Campus

Emulex Corporate Campus

Emulex Corporate Campus

Emulex Corporate Campus

Quick Facts
Tallest Panel:
33'0"
Largest Panel:
900 sqft
Heaviest Panel:
133,333 lbs
Construction Time:
150 days