Owens Brothers Concrete Batch Plant
Owens Brothers Concrete Plant
2005 Tilt-Up Achievement Award Winner
Manufacturing/Industrial Division
Tilt-Up's durability enable the owner of this new concrete batch facility to comply with city regulations.

TCA Member Participants

Submitted By :
Engineer:
LJB Inc. (Dayton, Ohio)
Lifting Hardware: Dayton Superior (Miamisburg, Ohio)
 

Since the operations of the building required a durable facility, the owner switched from a metal building to a concrete structure that enabled them to comply with city ordinances. The city required that the entire batch plant operations be enclosed within the building.

The manufacturer of the equipment would not allow any part of the enclosure to be in contact with the building. Because of this, the team used 3-D modeling to help fit equipment into tightly designed tolerances. The aggregate bin and cement silo/mixer were erected previously because of their heights. This required that the panels and roof structure were erected around them.

The city selected the color scheme of the project to provide a southwestern appearance – sandstone rose with blue metal roof panels. Since the original design called for metal wall and roof panels, the concrete panels had metal panel profile cast into the panels at the upper sections of the aggregate bin enclosure.

The building features stacked panels that reach a height of 66 feet-3 inches to enclose the aggregate bin. Removable roofs were used for servicing the aggregate bin and batch drum replacement. The mechanization that was designed into the project allows the plant to be operated by one person on slow days.

 

Related Projects

Guittard Chocolate (2003)
Valmark Industries (2003)
Location
Owens Brothers Concrete Batch Plant
Aurora, Colorado
Photos
Photo 1
Photo 2
Photo 3
Photo 4
Click to view larger image
Quick Facts
Project size:
5,600 sq.ft.
Tallest panel:
48' 3 "
Largest panel:
700 sq.ft.
Heaviest panel:
64,000 lbs
Construction time :
240 days