Hogan Office Building
Hogan Office Building
2005 Tilt-Up Achievement Award Winner
Office Division
Desiring a durable facility that offered aesthetic value, Tilt-Up was selected for this project because it met the city’s strict ordinance for the business park and would allow Hogan & Associates to market concrete to visitors of their facility.

TCA Member Participants

Submitted By :
General Contractor:
Hogan & Associates Construction
Tilt-Up Contractor:
Hogan & Associates Construction
Engineer:
ARW Structural Engineers (Ogden, Utah)
Cast-in Materials: Greenstreak, Inc. (St. Louis, Missouri)
Form Release: Nox-Crete Products Group (Omaha, Nebraska)
Bond Breaker: Nox-Crete Products Group
Lifting Hardware: Meadow Burke (Tampa, Florida)
 

Tilt-Up is considered a “green” product that would be locally produced and would offer the thermal mass needed to heat and cool the building through our ground source mechanical system. Forced out of their former office space to make way for a freeway, construction began in late fall with the structural work beginning in the dead of winter. A portable boiler was used to control the winter temperatures, which allowed work to continue through the worst part of the winter and complete the structural walls and the mural despite heavy snowfall. Construction also required careful management to ensure the timber frames were compatible with the concrete work.

The architectural treatments were a rough bark wainscot around the entire building (except the mural wall), a simple chamfer pattern, a mixture of timber frame elements and concrete, exposed aggregate accomplished through concrete retarder, and a standing seam metal roof. The concrete was kept a plain color to retain a natural and durable look.

Design elements in the wall include a formliner, a mural depicting construction elements, exposed aggregate, and exposed interior walls.

 

Related Projects

Security Central (2004)
CitiMortgage Operations Center (2004)
Chevron/Texaco (2004)
Orr Safety Corporation (2002)
Location
Hogan Office Building
Centerville, Utah
Photos
Photo 1
Photo 2
Photo 3
Photo 4
Photo 4
Click to view larger image
Quick Facts
Project size:
21,500 sq.ft.
Tallest panel:
24' 0"
Largest panel:
504 sq.ft.
Heaviest panel:
51,500 lbs
Construction time :
300 days