2005 Tilt-Up Achievement Award Winner
Office Division
The developer agreed to build a Class A office building – the first in the Lee’s Summit community –that would serve as a showcase for architectural Tilt-Up construction.

TCA Member Participants

Submitted By :
General Contractor:
Meyer Bros. Building Co. (Lee's Summit, Missouri)
Tilt-Up Contractor:
Meyer Bros. Building Co.
Engineer:
LJB Inc. (Dayton, Ohio)
Cast-in Materials: Scott System (Denver, Colorado)
Bond Breaker: Dayton Superior (Miamisburg, Ohio)
Lifting Hardware: Meadow Burke (Tampa, Florida)
 

The major tenant, Meyer Brothers Building Company, needed a new facility to locate its business office. Since Tilt-Up construction is a major component of Meyer Brothers work, the developer agreed to build a Class A office building – the first in the Lee’s Summit community –that would serve as a showcase for architectural Tilt-Up construction. The use of two different types of exposed aggregate, cast-in thin brick, cast-in thin block and painted finishes combined to provide a useful sales and marketing tool for both the construction and development business.

The height of the panels plus the numerous exterior accent panels required special attention to sequencing of panel construction on the relatively small floor slab. The radiused entrance panel is concave, meaning curved into the building structure.

Composite floor framing provided an economical system to maximize clear height while minimizing overall building height to meet local and Federal Aviation Administration regulations. Accent panels with various architectural treatments surround the perimeter of the building and are offset from the exterior face at varying depths. Two-inch recesses were cast into the panel to allow for application of cast-stone sills. Spandrel glass was incorporated in the recessed portion of the building’s side and rear walls.

A two-inch fascia wythe was cast using integrally colored concrete and structurally bonded to the main structural panel wythe. In order to achieve the masonry treatment on all sides, two identical panels were cast with the face shells and set back-to-back. This required precise control so that all openings and masonry joints would align. These panels also include several large openings, with 90-degree return pieces along every edge and jamb

 

Related Projects

Dade Paper (2004)
Mia Shoes (2004)
Stapleton Business Center, Building E1 (2003)
Stapleton Business Center, Building B4 (2002)
Orr Safety Corporation (2002)
Location
Business Exchange
Lee’s Summit, Missouri
Photos
Photo 1
Photo 2
Photo 3
Photo 4
Click to view larger image
Quick Facts
Project size:
50,000 sq.ft.
Tallest panel:
51' 0"
Largest panel:
1,359 sq.ft.
Heaviest panel:
120,000 lbs
Construction time :
240 days