Tilt-Up Concrete Assn.
PO Box 204
113 First Street W
Mt. Vernon, Iowa 52314
T: (319) 895-6911
F: (320) 213-5555
Send email to TCA
Security Central
Security Central
2004 Tilt-Up Achievement Award Winner
Office Division
This was a special project for it wasn’t for a developer or a large company with unlimited funds. Instead, it was for a company that has worked hard for the last thirty years saving to have its own office and had limited dollars with which to spend. Tilt-Up honestly saved this job and really gave Security Central their dream.

TCA Member Participants

Submitted By:
Saunders Construction (Centennial, Colorado)
Owner:
Security Central
Architect:
Intergroup Architects (Littleton, Colorado)
Engineer:
Monroe & Newell Engineers (Denver, Colorado)
General Contractor:
Saunders Construction
Tilt-Up Contractor:
Saunders Construction
Cast-in Materials:
Scott System, Inc. (Denver, Colorado)
Bond Breaker:
 

The 15,134-square-foot Security Central office building is an example of a project that was well thought out and executed, especially in its use of thin brick. The use of Tilt-Up construction provided a quicker schedule and was more cost-effective than competing methods.

Judges commented on the Tilt-Up technology employed and attention to detail that allowed the brick in the panels to be utilized so effectively. This project has elevated the use of Tilt-Up locally on small and office projects.

Site conditions were particularly challenging for this project. With a usable floor slab of less than 5,500-square-feet, the team decided to construct an 11,000-square-foot casting bed in the parking lot that was eventually covered by asphalt paving. The 50,000-square-foot site had a slope, so the casting bed sloped in two directions. This required focused attention to the detailed panel articulation.

The owner’s desire for great exposure resulted in construction of an extremely tall two-story office building boasting panels that, at 41-feet, were almost tall enough to accommodate a third floor. Further, conventional brick columns and a sheet metal flashing were used to create a robust entry.

An effective use of both thin brick and conventional brick, the two systems match and most people think the entire building is traditional brick. Even more remarkable, the project was completed in six months through a harsh Colorado winter.

Location
Security Central
Progress Point Business Park
O'Fallon, MO 63304
Photos
Photo 1
Photo 2
Photo 3
Click to view larger image
Quick Facts
Total floor area:
15,134 sq.ft.
Total cost:
$75 / sq.ft.
Completed cost:
$85 / sq.ft.
Tallest panel:
41' - 0 "
Largest panel:
1,517 sq.ft.
Heaviest panel:
118,000 lbs
Shell construction :
164 days (w/ finishes)
Related Projects
CitiMortgage (2004)
Chevron/Texaco (2004)
Iron Bridge 1401 (2004)
The Berkeley Building (2004)