Mission College Learning Resource Center
Mission College Learning Center
2003 Tilt-Up Achievement Award Winner
Educational Division
The design team for the Mission College Learning Center choose to embrace the Tilt-Up wall panel system as a genuinely interesting and environmnetally-sound material.

TCA Member Participants

Owner:
Mission College
Bond Breaker:
Nox-Crete Products Group (Omaha, Nebraska)
Form Liners :
Greenstreak (St. Louis, Missouri)
 

Tilt-Up allowed for the creation of the 38,500-square-foot Mission College Learning Resource Center (LRC) in Santa Clara, Calif. in only 420 days.

The Best in Class winner in the Education category, it was important that the LRC -- a digital-era information bank and an important point of campus interaction – complement the existing cast-in-place structures on campus.

Flexibility and visibility required a large, uninterrupted floor area, well-suited to Tilt-Up construction. Architecturally, the design team choose to embrace the Tilt-Up wall panel system as a genuinely interesting and environmnetally-sound material. Such a unique design approach resulted in the empowerment of interlocked joints (particularly the “log cabin” corner condition), interrupted profiles (at 25-feet, panel sizes are about the width of an urban lot, emphasizing the dimension by openings at the parapet, as well as joints introduced at appropriate scale and proportion without artifice), and illuminated connections (frosted glass panels are installed at panel joints).

A formliner was used to provide a strong graphic rhythm, while integral colored concrete matches the existing poured-in-place concrete structures on campus. Further, metal sunscreens and canopies provide daylight control and passive cooling.

Location
Mission College Learning Resource Center
Santa Clara, California
Photos
Photo 1
Photo 2
Photo 3
Photo 4
Photo 5
Photo 6
Click to view larger image
Quick Facts
Total floor area:
38,500 sq.ft.
Total cost:
$190.26 / sq.ft.
Comp cost:
$192.00 / sq.ft.
Tallest panel:
24' - 0 "
Largest panel:
612 sq.ft.
Heaviest panel:
55,080 lbs
Shell construction:
420 days