Seawalk Performance Pavilion
Seawalk Performance Pavilion
2002 Tilt-Up Achievement Award Winner
Special Projects Division
One of the smallest winners ever of a TCA Tilt-Up Award, the Seawalk Performance Pavilion relies on Tilt-Up to provide protection against storm winds and wave action.

TCA Member Participants

Submitted By:
The Haskell Company
Owner:
City of Jacksonville Beach
Architect: The Haskell Company
General Contractor:
The Haskell Company
Tilt-Up Contractor:
The Haskell Company
Bond Breaker :
Nox-Crete Products Group (Omaha, Nebraska)
Accessories:
Meadow Burke (Tampa, Florida)
 

The Haskell Company employed Tilt-Up construction to ensure durability for the Seawalk Performance Pavilion in Jacksonville Beach, one of three winners in the Special Projects category. In addition to creating a unique and inviting amphitheater to be enjoyed by the public, requirements for the project included strength against storm winds and wave action, and durability against corrosion.

According to Alan Wilson, Haskell's architect for the project, it was natural to select Tilt-Up construction because load-bearing concrete was the only method capable of providing unique architectural treatment in the form of a durable structure.

The three-dimensional building, boasts a sculptured quality, complete with sweeping curved panels tops, mimicking the form of nearby dunes or ocean waves. The stage roof, which cantilevers 13-feet, reaches out to the audience like a wave preparing to break onto the beach.

Flanking sound wings, where speakers are placed for performances, and rear panels curve outward out-of-plane more than three feet, adding to the structure's sculptural quality.

For more information on this special project, contact Alan Wilson at (904) 791-4500.

Location
Seawalk Performance Pavilion
Jacksonville Beach, Florida
Photos
Photo 1
Photo 2
Photo 3
Photo 4
Click to view larger image
Quick Facts
Total floor area:
5,280 sq.ft.
Tallest panel:
44' - 0 "
Heaviest panel:
128,000 lbs
Construction time:
141 days