Hope Lutheran Church
Hope Lutheran Church
2002 Tilt-Up Achievement Award Winner
Religious Division
The design for this structure expresses extreme creativity of form for Tilt-Up panels.

TCA Member Participants

Submitted By: GCM Contracting Solutions
Owner:
Hope Lutheran Church
Architect: Sheeley Architects
Engineer: Sheeley Architects
General Contractor:
Surety Construction Company
Tilt-Up Contractor:
GCM Contracting Solutions
Tilt-Up Erector: Sunshine Specialties, Inc. (Orlando, Florida)
Bond Breaker :
Nox-Crete Products Group (Omaha, Nebraska)
 

Site-cast Tilt-Up concrete was selected for the 15,000-square-foot structure by the architect as the most cost- effective method for construction due to the design complexity.

The architect was convinced that in addition to solving the design, Tilt-Up construction would also offer aesthetics that were advantageous for the site. The design for this structure expresses extreme creativity of form for Tilt-Up panels.

Every panel on the project has either a convex or a concave radius at the top ranging from 12-ft. to 40-ft. These radii project into the air projecting the imagery appropriate for the building type.

For more information on this project, contact Robert W. Brown at (941) 334-8800.

Location
Hope Lutheran Church
Bonita Springs, Florida
Photos
Photo 1
Photo 2
Photo 3
Click to view larger image
Quick Facts
Total floor area:
15,000 sq.ft.
Tallest panel:
61' - 10.5"
Heaviest panel:
112,200 lbs
Construction time:
175 days